This section describes the general device installation process. Before installing device, you need to determine the installation mode according to installation environment. After unpacking and inspecting the device, you need to install the chassis, boards, fibers, and cables in sequence, and then check the installation result. After determining that the installation is correct, you can power on the device and then check fiber connections.
Table 1 lists the general installation process.
Installation Process |
Description |
---|---|
Preparing for the installation |
Before installing a device, plan and construct the installation space and confirm the installation method based on the requirements of device operation environment. This is a prerequisite for smooth installation, commissioning, and stable running of the device. For details, see section Preparing for the Installation in Hardware Installation and Maintenance. |
Unpacking a device |
After the project starts, the project supervisor should unpack and check the device together with the customer representative. For details, see section Unpacking a Device in Hardware Installation and Maintenance. |
Installing a chassis |
The installation method of the chassis varies according to the installation environment. For details, see section Installing a Chassis in Hardware Installation and Maintenance. |
Installing components |
Generally, the components are installed in the chassis. If the components are delivered separately, see section Installing Components in Hardware Installation and Maintenance. |
Planning cable routing |
To ensure that power cables are connected in order, you are advised to plan power cable routing. For details, see section Planning Cable Routing in Hardware Installation and Maintenance. |
Installing cables |
The methods of installing cables vary according to the installation environment of the chassis. For details, see section Installing Cables in Hardware Installation and Maintenance. |
Checking the installation |
To ensure normal and stable running of a device, you need to check the installation of the device after all hardware is installed. For details, see section Post-Installation Check in Hardware Installation and Maintenance. |
Performing a power-on check |
Before powering on a device, you need to check the voltage and fuse capacity of the external power supply. After the power-on, you need to check whether the device is running normally by observing the indicators. For details, see section Power-on Check in Hardware Installation and Maintenance. |
Maintaining a device |
Faulty fuses and other electronic components can only be replaced by professionals authorized by Huawei. For details, see section Maintaining a Device in Hardware Installation and Maintenance. |